Week_7

May 16-22: Ceilings inside and over the veranda and walkway outside are installed, walls plastered, windows and doors installed, and skilled carpenters begin to make classroom furniture onsite.
May 16: Ceiling installation -- covering straps and the fillets installed in two classrooms, office, and storeroom.
The third classroom has been covered. Waiting for the fillets.
We also started working on the veranda and the overhang.
May 17: We finished work on the ceiling of the third classroom, and continued work on the veranda and the exterior (shot-out) of the building.
The front veranda.
Skilled carpenters are now on site in Koromasilaia to start crafting the classroom furniture, marking another important step toward completion.
May 19: The ceiling installation is expected to be completed today.
Finished ceiling work on the veranda.
Working on the back shot of the school.
The carpenters are busy with the furniture work (building desks and chairs).
May 20: We started plastering walls inside today.
Plastering going on.
We did two classrooms today.
Cleaning took place around the building.
A sample of the classroom furniture being built.