Week_2

April 11-17. Mixing cement, forming cement blocks, and working on the foundation.
April 11: Mixing of the cement.
Cement blocks being made one-by-one in a form and then put out in the sun to set and harden.
Delivery of granite stone that was bought.
Blocks set out in the sun.
April 12: Block mudding with some of the community people.
With the help of the community people and the workers, they are making the sand crate blocks manually.
The youth of the village are happy to participate in the construction of the senior secondary school in their community.
April 13: The community went and did sand mining, while the workers were laying blinding concrete on the foundation trench.
Sand pack. [note: they had to go all the way to Musaia town, which is over an hour away, over a rough road, to pull sand as it's the only place they can get enough sand for construction in the Kabala District.]
The workers laying blind concrete of the foundation trenches.
April 14: Finished the blind concreting on the foundation trenches.
Foundation block work starts tomorrow.